Headlines : * Shakib`s final Test in doubt amid protests and safety concerns   * Govt set to launch farm-to-market scheme today   * Syria state media says Israeli air strike hits Latakia   * Ex-mayor Atiqul Islam sent to jail in 3 murder cases   * UN report says 1.1 billion people in acute poverty   * Foreign Secretary seeks UN cooperation in combating illicit financial flows   * Dhaka seeks enhanced trade, economic cooperation with Ghana   * Traders seek 5pc duty waiver on import of soybean, palm oils   * Flood causes Tk 100 cr losses in Netrokona agriculture sector   * International Crimes Tribunal to start trial process from Thursday  

   National
Rooppur Nuke Plant`s 85pc works complete, go for power generation by 2025
  Date : 18-10-2024

Prime Minister Sheikh Hasina has called upon the Russian state-run ROSATOM to set up another nuclear power plant at Rooppur, if there is any scope for that.

The premier made the request when her at her official residence Ganabhaban in Dhaka, reports BSS.

Briefing the reporters after the meeting, Prime Minister`s Speech Writer Md Nazrul Islam said that Sheikh Hasina asked them to go for construction of new plants on the site of Rooppur Nuclear Power Plant (RNPP) after completion of the ongoing project.

She also pointed out that a technical survey needs to be conducted at the initial stage for setting up two new units.


The Prime Minister directed the authorities concerned to complete all the formalities of bringing back the "Spent Nuclear Fuel" of first and second units of RNPP to the Russian Federation.

In reply, the ROSATOM Director General gave assurance on behalf of the Russian government regarding the return of the Spent Nuclear Fuel produced by the first and second units to the Russian Federation, and promised to complete all the formalities for the return of the Spent Nuclear Fuel to the Russian Federation on time as per the instructions of the Prime Minister.

Bangladesh government and the Russian Federation government have already signed an inter-state agreement regarding the return of the Spent Nuclear Fuel of RNPP to the Russian Federation.

Sheikh Hasina thanked Russia for building energy security especially setting up this nuclear power plant in Bangladesh.

She said that it was the dream of Father of the Nation Bangabandhu Sheikh Mujibur Rahman to set up a nuclear power plant in Bangladesh, and it is being implemented and she thanked Russia for this.

Sheikh Hasina recalled the assistance of Russia in 1971 during the War of Liberation of Bangladesh and helped the country in its rebuilding process after the war.

The Prime Minister also greeted Russian President Vladimir Putin on his reelection.

Alexey Likhachev apprised the Prime Minister about the advancement of the RNPP and said by 2025, the RNPP will come into production and will be able to supplement electricity to the national grid.

He also said that 85 percent works of the RNPP has been completed.

The ROSATOM Director General also proposed to the government to build two new nuclear power units (Unit-3 and Unit-4) in RNPP area.

He said the construction of the new Unit-3 and Unit-4 should be started as soon as the construction of the first two units is completed.

In this context, Alexey Likhachev also said that the expansion of existing nuclear power projects is more profitable and reasonable from the financial point of view and in the light of technical and nuclear safety which is considered internationally.

He said that some 2,500 staffers, including Bangladeshi and Russians, have been working in the project who gained their expertise.

The Prime Minister asked the ROSATOM Director General to utilise the Bangladeshi expertise in nuclear power plant construction projects in different countries.

Alexey Likhachev said that due to the pandemic and sanction there were obstacles, but the work was carried out at the natural pace.

The Prime Minister said that the obstacles were avoided technically.

Science and Technology Minister Architect Yeafesh Osman, PM`s Principal Secretary M Tofazzel Hossain Miah and Science and Technology Secretary Md. Ali Hossain, among others, were present.

At present, the construction work of two units (1200 x 2=2,400 MW) each having a capacity of 1,200 MW in the RNPP area is in final stage.

The physical start-up of the first unit will begin in December this year, while commercial power generation will start in 2025 and 2026 from Unit-1 and Unit-2.



  
  সর্বশেষ
Hathurusingha’s suspension executed in BCB’s emergency meeting
Trials at 54 High Court benches from Sunday
Arrest warrant issued against Sheikh Hasina
Tarique Rahman will return to Bangladesh after legal fight

Chief Advisor: Md. Tajul Islam,
Editor & Publisher Fatima Islam Tania and Printed from Bismillah Printing Press,
219, Fakirapul, Dhaka-1000.
Editorial Office: 167 Eden Complex, Motijheel, Dhaka-1000.
Phone: 02-224401310, Mobile: 01720090514, E-mail: muslimtimes19@gmail.com